Part of the Carborough Downs Mine expansion project included the installation of a new 5km overland conveyor. Cell developed and designed the control system for the new conveyor system utilising the latest Rockwell RSLogix5000 software and Citect SCADA package whilst ensuring compliance with existing CHPP infrastructure and managing the seamless integration of the two systems. The design allowed for the programming and integration of a fieldbus conveyor pull wire system and reference to AS1755 Conveyors - Safety requirements.